Kiewit-Turner contracted CriticalArc to assist with the commissioning of the new $1.4B 11-building VA hospital campus in Denver, CO. CriticalArc provided commissioning coordination, troubleshooting, scheduling, overall process management for the construction phase, commissioning process development, implementation, and all project closeout reporting. This project spanned 2 years and was completed on time in 2018.

Image Credit: nbcnews.com
About This Project
Project Details
Client: Kiewit-Turner
Project: Department of Veterans Affairs - Denver VA Replacement Medical Center
Location: Denver, CO
Sq. Ft.: 2.2M
Construction Volume: $1.4B